The gap-closure plan: which work items bring solutions to confirmed readiness, who is responsible and what blocks them. Deadlines and owners are assigned by the technical lead.
Total tasks
12
Critical
6
No owner
11
With a deadline
0
the rest are N/A
Coordinate EW use at civilian site
Item: OB-03
Criterion: Regulator approval received
Legal review of interceptor UAV use with HE-frag warhead
Item: RG-01
Criterion: Legal team opinion
Check canopy #1 applicability to site geometry
Item: IZ-03
Criterion: Layout conclusion
Identify integration bus owner
Item: —
Criterion: Owner assigned for INT-01…09
Exclude boom barrier from project scope
Item: IZ-04
Criterion: Decision recorded in protocol
Sign NDA to obtain KOZ-U-SH details
Item: IZ-02
Criterion: Legal procedures completed
Request pricing for radars 96L6 and 1L122-1
Item: OB-01, OB-02
Criterion: Commercial offers received
Identify PTZ camera and thermal imager supplier
Item: PR-03
Criterion: Selection protocol signed
KOZ-U-SH adaptation to actual site conditions
Item: IZ-02
Criterion: Working documentation approved
Clarify mesh protection scope for 10 tanks
Item: IZ-01
Criterion: Bill of quantities signed
Clarify RockBox gabion layout
Item: IZ-05
Criterion: Scheme 1 adapted to site
Work out EW and zone monitoring compatibility
Item: OB-03, PR-01
Criterion: Tag operation confirmed under active jamming
| ID | Task | Item | Stage | Closure criterion | Owner | Deadline | Priority |
|---|---|---|---|---|---|---|---|
| T-01 | Coordinate EW use at civilian site | OB-03 | Analysis | Regulator approval received | Not assigned | N/A | Critical |
| T-02 | Legal review of interceptor UAV use with HE-frag warhead | RG-01 | Analysis | Legal team opinion | Not assigned | N/A | Critical |
| T-03 | Request pricing for radars 96L6 and 1L122-1 | OB-01, OB-02 | Solution selection | Commercial offers received | Not assigned | N/A | Critical |
| T-04 | KOZ-U-SH adaptation to actual site conditions | IZ-02 | Design | Working documentation approved | Chief engineer Rodchikhin | N/A | Critical |
| T-05 | Clarify mesh protection scope for 10 tanks | IZ-01 | Design | Bill of quantities signed | Not assigned | N/A | High |
| T-06 | Check canopy #1 applicability to site geometry | IZ-03 | Analysis | Layout conclusion | Not assigned | N/A | High |
| T-07 | Clarify RockBox gabion layout | IZ-05 | Design | Scheme 1 adapted to site | Not assigned | N/A | Medium |
| T-08 | Identify PTZ camera and thermal imager supplier | PR-03 | Solution selection | Selection protocol signed | Not assigned | N/A | High |
| T-09 | Work out EW and zone monitoring compatibility | OB-03, PR-01 | Trials | Tag operation confirmed under active jamming | Not assigned | N/A | High |
| T-10 | Identify integration bus owner | — | Analysis | Owner assigned for INT-01…09 | Not assigned | N/A | Critical |
| T-11 | Exclude boom barrier from project scope | IZ-04 | Analysis | Decision recorded in protocol | Not assigned | N/A | Low |
| T-12 | Sign NDA to obtain KOZ-U-SH details | IZ-02 | Analysis | Legal procedures completed | Not assigned | N/A | Critical |